[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953116,690,1,"单选题","总时差是在不影响( )的前提下，本工作可以利用的机动时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","其紧后工作最早开始",false,{"key":16,"text":17,"correct":14},"B","总工期",{"key":19,"text":20,"correct":14},"C","其紧后工作最迟开始",{"key":22,"text":23,"correct":24},"D","其紧后工作最早完成",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]