[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953113,690,1,"单选题","审查和批准所有承包商、供货商按合同要求提交的各自的总进度计划及年、季、月实施进度计划是( )阶段的进度控制任务。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程设计",false,{"key":16,"text":17,"correct":14},"B","招标投标",{"key":19,"text":20,"correct":14},"C","实施准备",{"key":22,"text":23,"correct":24},"D","实施",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]