[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953112":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953112,690,1,"单选题","已知 A、B工作的紧后工作为c、 D，其持续时间分别为3d、4d、2d、5d， A、B工作最早开始时间为第5d、第6d，则C工作最早开始时间为第( )d。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":14},"C","8",{"key":22,"text":23,"correct":24},"D","10",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]