[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},953096,690,1,"单选题","建设单位同意承包单位根据变更意向书要求提交的变更实施方案的，由( )发出变更指示。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程质量监督管理机构",false,{"key":16,"text":17,"correct":14},"B","建设行政主管部门",{"key":19,"text":20,"correct":14},"C","建设单位",{"key":22,"text":23,"correct":24},"D","监理机构",true,"",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]