[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953063,690,1,"单选题","开展初步设计的必备条件不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工总承包单位已办理各种外部协作条件的取证工作和完成科研、勘察任务，并转交设计单位",true,{"key":16,"text":17,"correct":18},"B","建设项目可行性研究报告经过审查，并已获得批准文件",false,{"key":20,"text":21,"correct":18},"C","建设项目业主已办理征地手续，并已取得建设用地规划许可证和建设用地红线图",{"key":23,"text":24,"correct":18},"D","建设项目业主已取得规划局提供的规划设计条件通知书、环保部门批准的环境影响评价报告书","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]