[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},953059,690,1,"单选题","工程设计单位编制的完工阶段设计报告的内容不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目工程设计规模、功能、运行条件",false,{"key":16,"text":17,"correct":18},"B","非标准图、重复调用的图纸等技术文件",true,{"key":20,"text":21,"correct":14},"C","建筑工程结构型式、设计标准、运用条件、结构体系、结构布置、材料、工程等使用寿命",{"key":23,"text":24,"correct":14},"D","施工中主要技术问题与处理结果、设计校核结果","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]