[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},953057,690,1,"单选题","工程施工阶段的设计管理包括：①建设项目业主委托工程监理单位审查施工图设计文件与图纸;②施工单位提出设计图中存在的问题和需要解决的施工技术难题;③建设项目业主、工程监理方、工程设计防、工程施工协商方，拟定解决方案;④组织工程设计单位向施工单位进行技术交底。正确的程序是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④",false,{"key":16,"text":17,"correct":14},"B","①→③→②→④",{"key":19,"text":20,"correct":21},"C","①→④→②→③",true,{"key":23,"text":24,"correct":14},"D","①→②→④→③","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]