[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},953050,690,1,"单选题","对于复杂的、采用新工艺新技术又缺乏设计经验的重大项目，可根据各个行业的特点，在初步设计方案设计基础上进行( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","扩大初步设计",true,{"key":16,"text":17,"correct":18},"B","方案设计",false,{"key":20,"text":21,"correct":18},"C","技术设计",{"key":23,"text":24,"correct":18},"D","总体设计","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目实施","建筑工程",0]