[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-122761":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},122761,69,2,"多选题","在运输建设项目的经济评价中，反映项目盈利能力的评价指标有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","内部收益率",true,{"key":16,"text":17,"correct":18},"B","利息备付率",false,{"key":20,"text":21,"correct":14},"C","财务净现值",{"key":23,"text":24,"correct":18},"D","偿债备付率",{"key":26,"text":27,"correct":14},"E","项目投资回收期","ACE","项目盈利能力主要指标包括：①财务内部收益率（FIRR），当该指标大于或等于所设定的财务基准收益率时，项目方案在财务上可考虑接受；②财务净现值（FNPV），当按照设定的财务基准收益率计算的财务净现值大于或等于零时，项目方案在财务上可考虑接受；③项目投资回收期（Pt），该指标测算结果越小，表明项目投资回收越快，抗风险能力越强。根据委托方要求还可测算项目的总投资收益率（ROI）、项目资本金净利润率（ROE）等辅助性指标。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 运输经济","经济金融",0]