[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953046":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953046,689,2,"多选题","可行性研究与初步可行性研究相比，这两个阶段的( )有明显的区别。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","构成与内容",false,{"key":16,"text":17,"correct":18},"B","目的与作用",true,{"key":20,"text":21,"correct":18},"C","研究方法",{"key":23,"text":24,"correct":18},"D","研究论证重点",{"key":26,"text":27,"correct":18},"E","深度要求","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目决策","建筑工程",0]