[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-953036":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},953036,689,2,"多选题","初步可行性研究的主要内容包括( )等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资源利用效率分析",false,{"key":16,"text":17,"correct":18},"B","主要原材料的来源和其他建设条件",true,{"key":20,"text":21,"correct":18},"C","项目建设与运营的实施方案",{"key":23,"text":24,"correct":18},"D","投资初步估算、资金筹措与投资使用计划初步方案",{"key":26,"text":27,"correct":18},"E","财务效益和经济效益的初步分析","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"投资建设项目决策","建筑工程",0]