[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},952864,689,1,"单选题","初步可行性研究、可行性研究报告的编制，与初步可行性研究、可行性研究的评估，是项目前期工作的两项重要内容，二者的相同点是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承担主体相同",false,{"key":16,"text":17,"correct":18},"B","出发点一致",true,{"key":20,"text":21,"correct":14},"C","决策时序和作用相同",{"key":23,"text":24,"correct":14},"D","评估角度和任务相同","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]