[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},952820,689,1,"单选题","下列选项中，( )在项目预算中要单独列出，不能分散到具体费用项目之下，否则，项目班子就会失去对支出的控制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算进度款",false,{"key":16,"text":17,"correct":18},"B","预算应急费",true,{"key":20,"text":21,"correct":14},"C","保证金",{"key":23,"text":24,"correct":14},"D","预付款","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]