[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952819":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},952819,689,1,"单选题","建设项目的主要风险中，( )是指由于项目存在众多参与方，各方的动机和目的不一致将导致项目合作的风险，影响项目的进展和项目目标的实现。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管理风险",false,{"key":16,"text":17,"correct":14},"B","政策风险",{"key":19,"text":20,"correct":21},"C","组织风险",true,{"key":23,"text":24,"correct":14},"D","社会风险","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]