[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952816":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},952816,689,1,"单选题","建设方案经济比选的前提条件是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全性原则",false,{"key":16,"text":17,"correct":14},"B","适用性原则",{"key":19,"text":20,"correct":21},"C","可比性原则",true,{"key":23,"text":24,"correct":14},"D","经济性原则","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]