[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952809":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},952809,689,1,"单选题","当某建设项目的计算期大于( )年时，可以把此建设项目近似当做计算期无限的建设项目进行经济比选。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":21},"C","50",true,{"key":23,"text":24,"correct":14},"D","80","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]