[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},952807,689,1,"单选题","下列选项中，( )往往仅对项目进行初步的比选，没有考虑不同投资、不同收益、不同计算期对项目产生的影响。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","净现值比较法",true,{"key":16,"text":17,"correct":18},"B","差额投资内部收益率法",false,{"key":20,"text":21,"correct":18},"C","效益\u002F费用比较法",{"key":23,"text":24,"correct":18},"D","最低价格比较法","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]