[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952698":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},952698,689,1,"单选题","采用( )，不需要详细的工程设计资料，只需知道工艺流程和生产规模，计算简单、速度快，但要求类似工程的资料可靠，条件基本相同，否则误差就会增大。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位生产能力估算法",false,{"key":16,"text":17,"correct":14},"B","比例估算法",{"key":19,"text":20,"correct":21},"C","生产能力指数估算法",true,{"key":23,"text":24,"correct":14},"D","指标估算法","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]