[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},952636,689,1,"单选题","厂(场)址方案比选主要考虑的内容中不包括的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","运营费用",false,{"key":16,"text":17,"correct":18},"B","技术条件",true,{"key":20,"text":21,"correct":14},"C","建设条件",{"key":23,"text":24,"correct":14},"D","投资费用","",{"id":6,"name":27,"category":28,"favorite":29},"投资建设项目决策","建筑工程",0]