[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-952350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},952350,688,1,"单选题","国家发展改革委核准项目申请报告时，需要征求国务院行业主管部门意见的，国务院行业主管部门应在接到相关材料之日起( )个工作日内，向国家发展改革委提出书面意见。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","23","",{"id":6,"name":27,"category":28,"favorite":29},"宏观经纪政策","建筑工程",0]