[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-951457":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},951457,687,1,"单选题","建设项目施工和地质勘查需要临时占用耕地的，土地使用者应当自临时用地期满之日起（ ）内恢复种植条件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6个月",false,{"key":16,"text":17,"correct":18},"B","1年",true,{"key":20,"text":21,"correct":14},"C","18个月",{"key":23,"text":24,"correct":14},"D","2年","根据《土地管理法实施条例》第二十八条的规定，建设项目施工和地质勘查需要临时占用耕地的，土地使用者应当自临时用地期满之日起1年内恢复种植条件。",{"id":6,"name":27,"category":28,"favorite":29},"土地权利理论与方法","建筑工程",0]