[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-948367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},948367,684,1,"单选题","当（ ）时，可以利用拟用地界址点坐标与控制点、地物点坐标，计算拟用地界址点相对于控制点、地物点的距离等有关数据，作为关系距离法放样数据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目用地条件提供拟用地界址点坐标",true,{"key":16,"text":17,"correct":18},"B","建设项目用地条件提供拟用地界址点相对于控制点及地物点的距离和角度等有关数据",false,{"key":20,"text":21,"correct":18},"C","建设项目用地条件只提供用地图纸，而没有提供拟用地界址点坐标或拟用地界址点相对于控制点及地物点的距离和角度等有关数据",{"key":23,"text":24,"correct":18},"D","建设项目用地条件提供拟用地界址点坐标和用地图纸","建设项目用地条件提供拟用地界址点坐标时，利用拟用地界址点坐标与控制点坐标，计算拟用地界址点相对于控制点的角度、距离等有关数据，作为极坐标法放样数据；利用拟用地界址点坐标与控制点、地物点坐标，计算拟用地界址点相对于控制点、地物点的距离等有关数据，作为关系距离法放样数据；利用拟用地界址点坐标与控制点、地物点坐标，计算拟用地界址点相对于控制点、地物点的角度等有关数据，作为前方交会法放样数据。",{"id":6,"name":27,"category":28,"favorite":29},"地籍调查","建筑工程",0]