[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-948080":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},948080,684,1,"单选题","GPS测量外业实施中，主要工作是进行技术设计和选点埋石的阶段是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","外业观测",false,{"key":16,"text":17,"correct":14},"B","野外测量",{"key":19,"text":20,"correct":21},"C","外业准备",true,{"key":23,"text":24,"correct":14},"D","野外探测","GPS测量外业实施包括外业准备、数据观测和成果整理三个阶段。其中，外业准备阶段的主要工作是进行技术设计和选点埋石。",{"id":6,"name":27,"category":28,"favorite":29},"地籍调查","建筑工程",0]