[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-947651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},947651,683,1,"单选题","桩入土( )以上时，严禁用打桩机行走或回转动作来纠正桩的倾斜度。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1m",false,{"key":16,"text":17,"correct":14},"B","1.5m",{"key":19,"text":20,"correct":14},"C","2.5m",{"key":22,"text":23,"correct":24},"D","3m",true,"",{"id":6,"name":27,"category":28,"favorite":29},"桩机操作工","建筑工程",0]