[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-946527":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},946527,677,1,"单选题","为确保冬期施工起重机械设备安全使用，春季冻土融化，应当随时观察设备 基础是否发生( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","裂缝",false,{"key":16,"text":17,"correct":14},"B","倾斜",{"key":19,"text":20,"correct":21},"C","沉降",true,{"key":23,"text":24,"correct":14},"D","积水","",{"id":6,"name":27,"category":28,"favorite":29},"建筑起重机械司机（塔式起重机）","建筑工程",0]