[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-945237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},945237,672,1,"单选题","行走式塔式起重机轨道的轨距允许偏差为设计值的( ),最大允许偏差为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","±1‰、±5mm",false,{"key":16,"text":17,"correct":18},"B","±1‰、±6mm",true,{"key":20,"text":21,"correct":14},"C","±2‰、±5mm",{"key":23,"text":24,"correct":14},"D","±2‰、±6mm","",{"id":6,"name":27,"category":28,"favorite":29},"建筑起重机械安装拆卸工","建筑工程",0]