[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-109296":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},109296,67,2,"多选题","按投入要素划分，项目融资风险包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","政治风险",false,{"key":16,"text":17,"correct":18},"B","人员风险",true,{"key":20,"text":21,"correct":18},"C","时间风险",{"key":23,"text":24,"correct":18},"D","技术风险",{"key":26,"text":27,"correct":14},"E","信用风险","BCD","本题考查项目融资风险。按投入要素划分，项目融资风险可分为人员风险、时间风险、资金风险、技术风险、其他风险。政治风险和信用风险属于按照项目风险的表现形式划分的风险。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 农业经济","经济金融",0]