[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-108970":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},108970,67,2,"多选题","下列属于投资项目评估的时间比较法的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投资收益率法",false,{"key":16,"text":17,"correct":18},"B","静态投资回收期法",true,{"key":20,"text":21,"correct":18},"C","动态投资回收期法",{"key":23,"text":24,"correct":18},"D","增量比较法",{"key":26,"text":27,"correct":18},"E","抽样调查法","BCDE","本题考查投资项目评估的方法。投资项目评估定量分析中的时间比较法包括：静态投资回收期法、动态投资回收期法、增量比较法、抽样调查法。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 农业经济","经济金融",0]