[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-108551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},108551,67,1,"单选题","完工风险是按照（ ）划分的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目风险的阶段性",false,{"key":16,"text":17,"correct":18},"B","项目风险的表现形式",true,{"key":20,"text":21,"correct":14},"C","项目的投入要素",{"key":23,"text":24,"correct":14},"D","项目的输出结果","项目融资时，按照项目风险的表现形式划分为：信用风险、完工风险、生产风险、技术风险、资源风险、能源和原材料供应风险、经营管理风险、市场风险、金融风险、政治风险、环境保护风险。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 农业经济","经济金融",0]