[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-108516":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},108516,67,1,"单选题","在项目评估过程中，利用净年值法、净现值法、净现值率法对不同项目所含的全部因素进行方案比较的前提是各比选项目的()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","净现值相同",false,{"key":16,"text":17,"correct":14},"B","流动比率相同",{"key":19,"text":20,"correct":21},"C","计算期相同",true,{"key":23,"text":24,"correct":14},"D","速动比率相同","当各比选项目的计算期相同时，按照不同项目所含的全部因素(包括效益和费用两个方面)进行方案比较，可以用差额投资内部收益率法、净年值法、净现值法和净现值率法。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 农业经济","经济金融",0]