[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-107920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},107920,67,1,"单选题","从效益—成本比率角度来讲，如果一个项目可行，则（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","B／C\u003C1",false,{"key":16,"text":17,"correct":18},"B","B／C>1",true,{"key":20,"text":21,"correct":14},"C","B／C=1",{"key":23,"text":24,"correct":14},"D","B／C=0","本题考查项目盈利能力分析。效益—成本比率指项目现金流入的现值之和与现金流出的现值之和的比率。当（B／C）大于1时，则说明项目的净现值大于0，项目可行。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 农业经济","经济金融",0]