[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-107918":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},107918,67,1,"单选题","考虑到项目的动态情况，项目计算期一般都在（ ）之间，有时会小于项目的经济寿命期。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1～5年",false,{"key":16,"text":17,"correct":14},"B","5～10年",{"key":19,"text":20,"correct":14},"C","10～15年",{"key":22,"text":23,"correct":24},"D","10～20年",true,"本题考查项目财务评价的指标体系。考虑到项目的动态情况，项目计算期一般都在10～20年之间，有时会小于项目的经济寿命期。",{"id":6,"name":27,"category":28,"favorite":29},"(中级) 农业经济","经济金融",0]