[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-944575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},944575,669,1,"单选题","装设连墙件时，应保证立杆的( )要求。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","稳定",false,{"key":16,"text":17,"correct":14},"B","扣紧",{"key":19,"text":20,"correct":14},"C","强度",{"key":22,"text":23,"correct":24},"D","垂直度",true,"",{"id":6,"name":27,"category":28,"favorite":29},"建筑架子工","建筑工程",0]