[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-943263":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},943263,666,3,"判断题","装设临时接地线，必须在停电设备确实无电后进行，连 接时，先接接地端，然后接线路或设备端，拆除时，先拆 接地端，再拆除线路或设备端。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"",{"id":6,"name":21,"category":22,"favorite":23},"建筑电工","建筑工程",0]