[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-942869":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},942869,666,2,"多选题","建设工地的临时用电设备和线路（）必须由电工完 成，并应有人监护。电工等级应同工程的难易程度和技术 复杂性相适应。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采购",false,{"key":16,"text":17,"correct":18},"B","安装",true,{"key":20,"text":21,"correct":18},"C","巡检",{"key":23,"text":24,"correct":18},"D","维修",{"key":26,"text":27,"correct":14},"E","拆除","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"建筑电工","建筑工程",0]