[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-942834":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},942834,666,2,"多选题","施工现场供电系统保护(PE 线)设置重复接地的部位是( )以及塔式起重机、施工升降机、物料提升机、混凝土搅拌站等大型施工机械设备开关箱处。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","总配电箱(配电柜)处",true,{"key":16,"text":17,"correct":14},"B","各分路分配电箱处",{"key":19,"text":20,"correct":14},"C","各分路最远端用电设备开关箱",{"key":22,"text":23,"correct":24},"D","用电设备处",false,{"key":26,"text":27,"correct":24},"E","用电设备金属物","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"建筑电工","建筑工程",0]