[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94248":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94248,64,2,"多选题","对于生产性项目，建设实施阶段的工作内容有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","勘察设计",true,{"key":16,"text":17,"correct":14},"B","建设准备",{"key":19,"text":20,"correct":14},"C","施工安装",{"key":22,"text":23,"correct":14},"D","生产准备工作",{"key":25,"text":26,"correct":27},"E","竣工验收",false,"ABCD","此题考查工程建设实施阶段的工作内容。建设实施阶段的工作内容主要包括：勘察设计、建设准备、施工安装。对于生产性项目，在施工安装后期，还需要进行生产准备工作。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]