[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94226":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94226,64,2,"多选题","由于发包人原因导致的延误，承包人有权获得工期顺延和（或）费用加利润补偿的情况有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人增加合同工作内容",true,{"key":16,"text":17,"correct":14},"B","发包人迟延提供材料",{"key":19,"text":20,"correct":14},"C","提供图纸延误",{"key":22,"text":23,"correct":24},"D","异常恶劣气候条件",false,{"key":26,"text":27,"correct":14},"E","发包人变更交货地点","ABCE","由于发包人原因导致的延误，承包人有权获得工期顺延和（或）费用加利润补偿。其包括：①增加合同工作内容；②改变合同中任何一项工作的质量要求或其他特性；③发包人迟延提供材料、工程设备或变更交货地点；④因发包人原因导致的暂停施工；⑤提供图纸延误；⑥未按合同约定及时支付预付款、进度款；⑦发包人造成工期延误的其他原因。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]