[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94224":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94224,64,2,"多选题","下列关于承包人索赔的说法，不正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人应在知道或应当知道索赔事件发生后28天内，向监理人递交索赔意向通知书",false,{"key":16,"text":17,"correct":14},"B","承包人应在发出索赔意向通知书后28天内，向监理人递交正式索赔通知书",{"key":19,"text":20,"correct":21},"C","监理人应在收到索赔通知书的进一步证明材料后的28天内，将索赔处理结果答复承包人",true,{"key":23,"text":24,"correct":14},"D","承包人接受索赔处理结果，发包人应在做出索赔处理结果答复后28天内完成赔付",{"key":26,"text":27,"correct":21},"E","承包人接受索赔处理结果，发包人应在做出索赔处理结果答复后42天内完成赔付","CE","A项，承包人应在知道或应该知道索赔事件发生后28天内，向监理人递交索赔意向通知书，并说明发生索赔事件的事由。B项，承包人应在发出索赔意向通知书后28天内，向监理人递交正式的索赔通知书，详细说明索赔理由以及要求追加的付款金额和（或）延长的工期，并附必要的记录和证明材料。C项，监理人应在收到索赔通知书或有关索赔的进一步证明材料后42天内，将索赔处理结果答复承包人。DE两项，承包人接受索赔处理结果，发包人应在做出索赔处理结果答复后28天内完成赔付。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]