[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94222":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94222,64,2,"多选题","在工程施工合同履行过程中，属于变更范围的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","改变合同中任何一项工作的质量",true,{"key":16,"text":17,"correct":18},"B","重新检验隐蔽工程",false,{"key":20,"text":21,"correct":14},"C","改变合同工程的基线",{"key":23,"text":24,"correct":14},"D","改变合同中任何一项工作的施工时间",{"key":26,"text":27,"correct":14},"E","为完成工程需要追加的额外工作","ACDE","变更范围如下：①取消合同中任何一项工作，但被取消的工作不能转由发包人或其他人实施；②改变合同中任何一项工作的质量或其他特性；③改变合同工程的基线、标高、位置或尺寸；④改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序；⑤为完成工程需要追加的额外工作。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]