[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94220":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94220,64,2,"多选题","依据FIDIC《施工合同条件》规定，工程师的职权范围包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","修改进度计划",false,{"key":16,"text":17,"correct":18},"B","批准使用暂列金额",true,{"key":20,"text":21,"correct":18},"C","发布暂停施工令",{"key":23,"text":24,"correct":18},"D","发布工程变更指令",{"key":26,"text":27,"correct":18},"E","审查承包商索赔要求","BCDE","此题考查FIDIC《施工合同条件》中工程师权力范围。FIDIC《施工合同条件》中明示的（咨询）工程师权力可概括为以下几方面。①工程质量控制：对运抵施工现场的材料、设备质量进行检查和检验等。②工程进度控制：审查批准承包商的施工进度计划；指示承包商修改施工进度计划；发布开工令、暂停施工令、复工令和赶工令。③工程付款控制：确定变更工程的估价；批准使用暂定金额和计日工；签发各种付款证书等。④施工合同管理：解释合同文件中的矛盾和歧义；批准分包工程（除劳务分包、采购分包及合同中指定的分包商对工程的分包）；发布工程变更指令；签发工程接收证书和缺陷责任证书；审核承包商的索赔；行使合同内必然引申的权力等。选项A不属于工程师权力范围的原因：工程师可以审查承包商提交的施工进度计划，但无权修改，可以指示承包商进行修改。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]