[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94219":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94219,64,2,"多选题","下列工程索赔事项中，属于承包人可提出利润索赔的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人未按合同约定及时支付预付款、进度款",true,{"key":16,"text":17,"correct":14},"B","发包人提供图纸延误",{"key":19,"text":20,"correct":14},"C","增加合同工作内容",{"key":22,"text":23,"correct":24},"D","法规变化引起的价格调整",false,{"key":26,"text":27,"correct":24},"E","不可抗力停工期间的照管和后续清理","ABC","此题考查承包人索赔内容。根据《标准施工招标文件》中的合同条款，承包人索赔原因及可补偿内容见下表： 选项A、B、C三种情况时，承包人可向发包人索赔工期、费用和利润；而选项D、E两种情况时，承包人只能索赔费用，不能索赔工期和利润。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]