[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94217":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94217,64,2,"多选题","下列事件中，属于由承包商原因引起的工期延误有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工组织不当，出现停工待料",true,{"key":16,"text":17,"correct":18},"B","施工图纸未能及时交付",false,{"key":20,"text":21,"correct":14},"C","劳动生产效率低",{"key":23,"text":24,"correct":18},"D","核装置污染",{"key":26,"text":27,"correct":14},"E","施工机械设备故障造成窝工","ACE","本题考查因承包商引起的工期延误。选项B属于因业主及工程师造成的工期延误；选项D的核装置污染属于不可控制因素引起的工期延误，都不属于承包商原因造成。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]