[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94189":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94189,64,2,"多选题","承包人提交的已完工程进度款支付申请中，应包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","截至本次付款周期末已实施工程的价款",true,{"key":16,"text":17,"correct":14},"B","变更金额",{"key":19,"text":20,"correct":21},"C","累计已调整的合同金额",false,{"key":23,"text":24,"correct":14},"D","本次应支付的预付款",{"key":26,"text":27,"correct":14},"E","本次扣减的质量保证金","ABDE","进度付款申请单内容包括:①截至本次付款周期末已实施工程的价款;②变更金额;③索赔金额;④本次应支付的预付款和扣减的返还预付款;⑤本次扣减的质量保证金;⑥根据合同应增加和扣减的其他金额。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]