[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94186":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94186,64,2,"多选题","由于发包人原因导致的延误，承包人有权获得工期顺延和（或）费用加利润补偿的情况包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","减少合同工作内容",false,{"key":16,"text":17,"correct":18},"B","改变合同中任何一项工作的质量要求或其他特性",true,{"key":20,"text":21,"correct":18},"C","发包人迟延提供材料、工程设备或变更交货地点",{"key":23,"text":24,"correct":18},"D","因发包人原因导致的暂停施工",{"key":26,"text":27,"correct":18},"E","未按合同约定及时支付预付款、进度款","BCDE","此题考查工程施工阶段进度管理相关内容。由于发包人原因导致的延误，承包人有权获得工期顺延和（或）费用加利润补偿。包括：①增加合同工作内容；②改变合同中任何一项工作的质量要求或其他特性；③发包人迟延提供材料、工程设备或变更交货地点；④因发包人原因导致的暂停施工；⑤提供图纸延误；⑥未按合同约定及时支付预付款、进度款；⑦发包人造成工期延误的其他原因。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]