[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94182":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94182,64,2,"多选题","根据《标准施工招标文件》，下列事件中，承包人向发包人既可索赔工期又可索赔费用的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","发包人原因导致的工程缺陷和损失",true,{"key":16,"text":17,"correct":14},"B","承包人遇到不利物质条件",{"key":19,"text":20,"correct":21},"C","不可抗力停工期间的照管和后续清理",false,{"key":23,"text":24,"correct":14},"D","施工过程发现文物",{"key":26,"text":27,"correct":21},"E","承包人遇到异常恶劣的气候条件","ABD","此题考查承包人索赔相关内容。《标准施工招标文件》中的合同条款，规定了承包人索赔原因及可补偿内容。选项A：因发包人原因导致工程质量缺陷，承包人可获得工期、费用和利润补偿。选项B：因不利物质条件，承包人可获得工期和费用补偿。选项C：因不可抗力停工期间的照管和后续清理，承包人只能获得费用补偿。选项D：因施工过程中发现文物和化石等，承包人可获得工期和费用补偿。选项E：因承包人遇到异常恶劣的气候条件，承包人只能获得工期补偿。故承包人向发包人既可索赔工期又可索赔费用的是选项A、B、D。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]