[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94181":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94181,64,2,"多选题","工程变更的范围和内容包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","取消合同中任何一项工作，被取消的工作转由发包人或其他人实施",false,{"key":16,"text":17,"correct":18},"B","改变合同中任何一项工作的质量或其他特性",true,{"key":20,"text":21,"correct":18},"C","改变合同工程的基线、标高、位置或尺寸",{"key":23,"text":24,"correct":18},"D","改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序",{"key":26,"text":27,"correct":18},"E","为完成工程需要追加的额外工作","BCDE","此题考查工程施工阶段工程变更范围。变更范围包括：①取消合同中任何一项工作，但被取消的工作不能转由发包人或其他人实施；②改变合同中任何一项工作的质量或其他特性；③改变合同工程的基线、标高、位置或尺寸；④改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序；⑤为完成工程需要追加的额外工作。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]