[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94180":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94180,64,2,"多选题","关于施工阶段承包人施工安全责任的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同约定的安全施工措施费用应遵守规定，并包含在相关工作的合同价格中",true,{"key":16,"text":17,"correct":18},"B","由于发包人原因造成承包人人员的工伤事故，应由承包人承担责任",false,{"key":20,"text":21,"correct":14},"C","承包人因采取合同未约定安全施工措施增加的费用，由监理人商定或确定",{"key":23,"text":24,"correct":14},"D","承包人对分包人人员的工伤事故承担责任",{"key":26,"text":27,"correct":14},"E","承包人应按监理人的指示制定应对灾害的紧急预案，报送监理人审批","ACDE","此题考查施工阶段承包人的安全管理责任。合同约定的安全作业环境及安全施工措施所需费用已包含在相关工作的合同价格中。承包人因采取合同未约定的安全作业环境及安全施工措施增加的费用，由监理人按商定或确定方式予以补偿。故选项A、选项C正确。承包人对其履行合同所雇佣的全部人员，包括分包人人员的工伤事故承担责任，但由于发包人原因造成承包人人员的工伤事故，应由发包人承担责任。故选项B错误，选项D正确。承包人应按合同约定的安全工作内容，编制施工安全措施计划报送监理人审批；按监理人指示制定应对灾害的紧急预案，报送监理人审批。故选项E正确。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]