[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94176":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94176,64,2,"多选题","在工程勘察合同履行中发生的下列情况，属勘察人违约的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人停止履行合同",false,{"key":16,"text":17,"correct":18},"B","勘察人未经发包人同意擅自分包勘察任务",true,{"key":20,"text":21,"correct":18},"C","勘察文件不符合法律及合同约定",{"key":23,"text":24,"correct":18},"D","勘察人未按合同计划完成勘察，从而造成工程损失",{"key":26,"text":27,"correct":18},"E","勘察人无法履行合同","BCDE","此题考查工程勘察合同履行中违约责任。在合同履行中发生下列情况之一的，属勘察人违约：①勘察文件不符合法律及合同约定；②勘察人转包、违法分包或者未经发包人同意擅自分包勘察任务；③勘察人未按合同计划完成勘察，从而造成工程损失；④勘察人无法履行或停止履行合同；⑤勘察人不履行合同约定的其他义务。选项A属于发包人违约的情况。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]