[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-94175":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},94175,64,2,"多选题","下列关于工程勘察合同履行中发包人主要义务的说法中，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","符合专用合同条款约定的开始勘察条件的，发包人应提前14天向勘察人发出开始勘察通知",false,{"key":16,"text":17,"correct":18},"B","勘察服务期限自开始勘察通知中载明的开始勘察日期起计算",true,{"key":20,"text":21,"correct":14},"C","发包人接收勘察文件之后，必须组织专家会进行审查",{"key":23,"text":24,"correct":18},"D","发包人对于勘察文件的审查期限，自文件接收之日起不应超过l4天",{"key":26,"text":27,"correct":14},"E","勘察人应当组织勘察技术交底会","BD","此题考查工程勘察合同履行中发包人主要义务。符合专用合同条款约定的开始勘察条件的，发包人应提前7天向勘察人发出开始勘察通知。勘察服务期限自开始勘察通知中载明的开始勘察日期起计算。故选项A错误，选项B正确。发包人接收勘察文件之后，可以自行或者组织专家会进行审查。故选项C错误。除专用合同条款另有约定外，发包人对于勘察文件的审查期限，自文件接收之日起不应超过14天。故选项D正确。发包人应当组织勘察技术交底会，由勘察人向发包人、监理人和施工承包人等进行勘察交底，对工程勘察意图、勘察文件和施工要求等进行系统的说明和解释。故选项E错误。",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 建筑与房地产经济","经济金融",0]